The Signature Bridge: the finish line that keeps moving

The Signature Bridge, the six white arches over Biscayne Boulevard where I-395 meets the bay, has been under construction since October 2017: 3,299 days so far. It was due in 2021. The finish date has moved 4 times and now says December 2029, and the cost has gone from $802 million to $866 million.

The Signature Bridge arches over I-395 under construction
The arches going up, 24 March 2026. Photo: Phillip Pessar, CC BY 4.0, via Wikimedia Commons

Under construction for

3,299 days

and 1,775 days past the first promised finish (end of 2021).

Every finish date so far

2021the original finish20242023 or 2024, depending on the document2026summer 2026, announced November 20222027late 2027, announced April 20232029?December 2029, quietly updated on FDOT's site in mid-2025

The plan against the time it's taking

Oct 2017: work startsTeal: the plan. Stripes: the rest. White line: today.Dec 2029?

Built in less time

Miami has another famously moving release date: Grand Theft Auto VI was announced in December 2023, slipped twice, and comes out on 19 November 2026. The bridge will still be going up. The real places behind Vice City.

Why it's late

  • The wind-load calculations in the first design used the wrong code, gust factor and drag coefficient: the arches as drawn would not have stood up to 140 mph winds, and the redesign used up 10 of the 18 months set aside for design (approved May 2019).
  • In November 2020 a broken valve at an on-site concrete plant let too much fly ash into concrete poured over three months; those sections were torn out and rebuilt.
  • Then the pandemic: steel and concrete arrived late, crews were short, and work stops around holidays and big events.
  • The contractors sued the design firm, HDR, saying its errors added $405 million; HDR settled for $12 million in April 2025 without admitting liability.

In January 2026 a concrete beam fell and injured six workers, five critically; in March 2026 a worker died in a fall from an overpass onto Biscayne Boulevard. FDOT stopped the work both times, OSHA opened inspections, and construction restarted in April 2026.

The bridge

Arch height325 ft (99 m), six arches
Length1,025 ft (312 m); longest span 650 ft (198 m)
Designed byDonald MacDonald Architects; built by the Archer Western–de Moya joint venture for FDOT
Cost$802 million at the start, $866 million now
Under itThe Underdeck: a planned park with water features, an amphitheater and gardens

Sources: en.wikipedia.org, miamitodaynews.com, miamitodaynews.com, nbcmiami.com, nbcmiami.com, miamitimesonline.com. The day count runs from FDOT's notice to proceed on 29 October 2017. Last checked 10 November 2026.